Checking horizontal datum metadata before alignment

Inspect the permit drawing header

Before any alignment, open the permit PDF or CAD file and locate the horizontal datum note. Typical entries read "NAD 83 (2011) State Plane NC 3200 ftUS" or "NAD 27 State Plane NC 3200 ftUS". Copy the exact wording into the project notes.

Inspect the survey metadata

Open the survey export (CSV, LandXML, or point file) and read the coordinate system tag. If the surveyor delivered a .prj or .xml sidecar, open it in a text editor and confirm the datum string matches the permit note character-for-character.

Compare and flag

Create a two-row comparison table:

Source Datum string
Permit NAD 83 (2011) State Plane NC 3200 ftUS
Survey NAD 83 (2011) State Plane NC 3200 ftUS

If the strings differ — even by a single parenthesis or epoch tag — flag the mismatch and do not proceed with alignment until the surveyor re-exports in the permit datum or the permit is reprojected.

Exception: intentional local grid

Some municipalities require the permit to be drawn in a local ground coordinate system while the survey is delivered in state plane. In that case, note the grid-to-ground scale factor and the base point in the project log, then apply the same factor during the fit transform so both layers share a common coordinate space.

Outcome

A documented datum agreement (or a recorded transformation) exists before any control points are selected, preventing a silent rotation or scale error from propagating through every offset measurement.