Length is measured along plan unless the question is about the pipe as built in three dimensions. Most permit comparisons use plan length, because that is what the drawing dimension shows. Slope calculations use horizontal run, which is also plan length. A surveyed 3D length is longer than plan length whenever the pipe falls, and mixing the two is a common source of small, persistent disagreements.

Label every length with its basis

On the comparison sheet, give each pipe two columns: plan length and surveyed length, with the basis written in the header. If only one is available, leave the other blank rather than filling it by assumption. A blank is honest; a converted number without the conversion shown is not.

Compare like with like

When checking against a permit dimension, use plan length. When checking a quantity or an as-built record that asks for actual pipe length, use the surveyed length and state that it includes fall. Do not compare a surveyed length to a permit plan dimension and call the difference an error.

A fictional example:

  • Pipe MH-6 to MH-7. Plan length 200.0. Invert drop 1.20. Surveyed 3D length 200.004.
  • Permit dimension 200.0 plan.
  • Comparison: plan difference 0.00; surveyed length exceeds plan by 0.004, which is the fall effect and is expected.

The reviewer records "permit match on plan basis" and does not raise a finding on the 0.004.

When the basis is genuinely unclear

Some records ask for "length" without saying which. In that case, write the basis you used next to the value and note the ambiguity for the next reviewer. If the record is a formal submittal, ask which basis the receiving party expects before submitting; do not guess and do not silently convert.

Each length on the sheet carries its basis, so a permit comparison and a quantity check no longer contradict each other.