Distinguishing accepted deviations from corrected geometry
Separating approved deviations from geometry corrections in the log
When the engineer accepts a non-compliant condition, the finding must not look like a corrected geometry item. Add a column “Resolution Type” with two values: “Corrected” or “Deviation Accepted.” Every row gets one. This single field drives the final certification summary.
Attaching the approval document to the deviation row
For each “Deviation Accepted” row, paste the RFI number, change order number, or engineer’s email date into the Approval Ref column. The redline PDF gets a green revision cloud on that balloon with the approval reference written inside.
Worked example: pipe cover deviation
Finding PP-02-RC-03-19: cover 2.1 ft vs. 2.5 ft minimum. Engineer approves via RFI-047 because existing utilities prevent deeper excavation. Reviewer sets Resolution Type = “Deviation Accepted,” Approval Ref = “RFI-047 2024-03-14.” The checklist row stays, but Verified column reads “Accepted per RFI-047.” Balloon 22 on C-301 gets a green cloud labeled “RFI-047.”
A separate row for the same pipe run, PP-02-RC-03-18 (slope corrected to 0.42%), gets Resolution Type = “Corrected” and Verified = “Yes” after the next survey confirms 0.42%.
Exception: deviation approved after construction complete
If the deviation is approved post-construction, the structure geometry never changes. The row remains “Deviation Accepted” with no subsequent survey comparison needed. The reviewer adds a note “As-built condition accepted” in the log.
The final report now shows two distinct counts: structures corrected to meet spec, and structures accepted with documented deviations.