Matching contractor responses to review identifiers
Linking contractor replies to the original finding ID
When the contractor returns a marked-up PDF or a response letter, each reply must reference the exact Finding ID from the review export. Create a two-column log: Finding ID and Contractor Statement. Paste every contractor sentence that addresses a finding into the log, preserving their wording. This log becomes the reconciliation record.
Matching by balloon number as a backup
If the contractor references only a balloon number, open the redline PDF, locate that balloon, read its Finding ID from the comment box, and enter the ID in the log. Do not guess; if the balloon has no ID, flag the reply as “Unmatched” and request clarification.
Worked example: MH-12 offset response
Contractor letter states: “Balloon 12 on C-301: MH-12 was staked per approved plans; survey error suspected.” The reviewer opens C-301, sees balloon 12 comment box reads PP-02-RC-03-12. The log entry becomes:
| Finding ID | Contractor Statement |
|---|---|
| PP-02-RC-03-12 | Balloon 12 on C-301: MH-12 was staked per approved plans; survey error suspected. |
The reviewer then pulls the original survey CSV, checks the MH-12 coordinate, and notes the measured offset remains 0.42 ft. The log now shows the contractor’s claim beside the verified measurement.
Exception: contractor bundles multiple findings in one statement
If one paragraph addresses balloons 12, 13, and 14, split the statement into three log rows, each with its own Finding ID. Copy the full paragraph into each row so context is preserved.
The reconciliation log now lets the reviewer accept, reject, or request data for every finding without hunting through PDFs.
Related: AsBuiltReview features.