Drawing corrections vs. field verification requests

Two different questions

One comment asks for a drawing correction, because the permit and the survey disagree about what was designed. Another asks for field verification, because the survey itself may not reflect what was built. Mixing them in one balloon leaves the reviewer unable to tell which action closes the item.

Splitting the entry

Write the drawing correction with the permit value, the surveyed value and the rule citation. Write the field verification request with the specific shot or measurement to confirm, and who should confirm it. Keep them on separate balloons even when they concern the same structure.

Suppose MH-4 shows a rim elevation difference of minus 0.15 feet against the permit. The drawing correction reads: S3-9 MH-4 rim: permit 1012.40 ft, survey 1012.25 ft, delta minus 0.15 ft, per MSD §5.1. The verification request reads: S3-10 MH-4 rim: re-shot rim shown as 1012.25 ft; confirm with field book page 14 before revision.

What each row tracks

In the log, the correction row closes when the revised sheet is issued. The verification row closes when the field confirmation is attached. A row that needs both actions stays open until both are recorded, and neither closure substitutes for the other.

The exception to watch

A structure that was clearly built out of place is set aside during the fit so it does not pull the alignment off. That does not mean the structure is approved. It means the fit error on the control points is not the right place to judge it. Give such a structure its own verification request, separate from any drawing correction, and say why it was set aside. The observable change is that each balloon on the sheet resolves to exactly one kind of action and one closure record.