Verifying that a corrected point reached the export

Confirming the corrected coordinate appears in the export

After the contractor submits a revised survey, the reviewer must verify that the specific point flagged in the original finding now shows the corrected value in the new export. Open the prior finding row, note the Structure Name and the coordinate fields (Northing, Easting, Rim Elev, Invert Elev). In the new export, filter for that Structure Name and compare each field.

Using the transform fit error as a sanity check

The review shows the transform used: rotation, scale, and fit error on control points. Before comparing coordinates, confirm the new survey’s fit error is within the project tolerance (typically 0.05 ft). A large fit error means the whole coordinate set may be shifted, making point-to-point comparison unreliable.

Worked example: MH-12 rim elevation correction

Original finding PP-02-RC-03-12 cited MH-12 rim elevation 2154.32 ft vs. permit 2154.75 ft (diff -0.43 ft). New survey export row for MH-12 shows Rim Elev 2154.74 ft. The reviewer calculates 2154.74 – 2154.75 = -0.01 ft, within the 0.05 ft tolerance. The transform fit error on the new survey is 0.03 ft. The reviewer marks the finding Verified in the checklist.

Exception: structure renamed between surveys

If the contractor renames MH-12 to MH-12A, the export filter on the old name returns nothing. Search the new export for the permit name cross-reference table (the review lists “Anything on the permit that the survey does not have”). Match the new name, then compare coordinates. Document the rename in the log.

The corrected point is now confirmed present in the export with values that satisfy the rule limit.