Writing a redline that identifies the affected run
Naming the run in the comment
A redline that says adjust slope is not actionable, because the crew cannot tell which pipe, in which direction, against what value. The comment must carry the run name as it appears on both the permit and the survey, the permit value, the surveyed value and the rule citation.
Matching by name first
Structures are matched by name, so MH-1 on the permit should meet MH-1 on the survey, and SSMH #4 should meet MH-4. When the names differ in form, write the pair in the comment so the match is auditable. A run between two matched structures is then identified by its endpoints.
A concrete entry
Suppose the permit shows run MH-1 to MH-4 at 0.60 percent slope, and the survey shows the same run at 0.50 percent. The county document in the library sets a warning at a 0.05 percent change.
Comment text: S3-7 Run MH-1 to MH-4 (SSMH #4 on survey): permit slope 0.60%, surveyed 0.50%, delta 0.10%. Exceeds warn 0.05% per Buncombe County MSD §4.2. Confirm field slope before issuing permit revision.
The same pattern covers length: S3-8 Run MH-4 to MH-9: permit length 84 ft, surveyed 81 ft, delta 3 ft, per §4.5.
Avoiding a vague handoff
If the survey shows a structure that the permit does not list, do not fold it into a run comment. Give it its own balloon and its own row, naming the survey structure exactly as shot. The observable change is that any crew member can pick up the sheet, find the named run, and see both values and the section that sets the limit.