As-Built Drawings Example: Manhole and Pipe Redlines
An as built drawings example should show the permitted condition, the surveyed condition, the calculated difference, and the disposition on one traceable sheet. In the practical example below, a reviewer checks one manhole and its connecting pipe, then carries each supported discrepancy into a redline worksheet without hiding the source values.
What should an as-built drawings example contain?
An as-built drawings example should contain a stable drawing reference, identifiable survey observations, side-by-side values, and a record of what happens next. A finished-looking line on a plan is weak evidence when nobody can tell which field shot supports it.
See the Federal Highway Administration implementation guide. The guide states, “As–built plans should be prepared and provided to the owner upon completion of the project.” This statement applies to the guide’s geosynthetic reinforced soil integrated bridge system (GRS-IBS) project context; it is not a universal acceptance rule. An example can demonstrate a traceable review method, but the governing contract and authority still determine the required deliverable.
See FHWA’s digital as-builts overview. FHWA describes traditional as-built drawings as recording field changes on paper plan sheets or PDFs while not capturing much additional information generated during design and construction. The source does not establish that every traditional as-built is incomplete, nor does it prescribe the redline symbols or worksheet fields used in this example; those are practical example conventions that must yield to project requirements.
What files does this worked example use?
This worked as-built example uses the repository’s fictional Woodfin Sewer Extension fixture: a permit network, a generated survey, and the application’s comparison logic. The permit fixture contains the following exact structure records:
{ name: "MH-2", x: 5248, y: 5032, rim: 2238.9, invIn: 2228.4, invOut: 2228.3 },
{ name: "MH-3", x: 5492, y: 4985, rim: 2234.2, invIn: 2223.33, invOut: 2223.23 },The east-coordinate check is 5,492 ft − 5,248 ft = 244 ft. That 244-foot result is only one coordinate component, so it must not be mislabeled as pipe length. A full plan distance would also use the 47-foot north-coordinate difference and the project’s coordinate basis.
The fixture also labels the run as an 8-inch PVC pipe and generates distinct rim and invert observations. Those details let us demonstrate a review row. They do not prove that a live file imported correctly, that the fictional coordinates represent a real site, or that any authority would accept the values.
How do you turn the example into a reviewable redline?
Turn the example into a reviewable redline by moving from identity to measurement to disposition. Each step should leave a short trail another reviewer can repeat.
- Freeze the source pair. Record the permit revision, survey file name, survey date, units, coordinate system, and vertical datum.
- Match the asset. Tie the MH-2 and MH-3 labels to the relevant survey observations. Preserve each point ID and raw description instead of replacing them with a plan name.
- Check plan position. Compare aligned eastings and northings. Report the total offset only after alignment and both components are verified.
- Check the profile. Pair upstream and downstream inverts by pipe and flow direction. Never use the nearest elevation simply because it produces a smaller difference.
- Open a numbered issue. Put the same issue number beside the cloud and in the worksheet. State the measured difference before applying a project limit.
- Record disposition. Leave the issue open, accept it with authority, or resolve it with a revised survey or drawing. Keep the original measured values.
The earlier guide to survey point IDs and structure names explains the matching step in detail. If the work is still exposed, the before-backfill field record lists the evidence worth collecting before access disappears.
What does the completed example worksheet look like?
The completed worksheet keeps geometry, elevation, and decision fields separate. Copy the headings below into a spreadsheet or issue log, then replace every fictional value with the project’s verified source data.
| Issue | Source and feature | Permit / survey comparison | Disposition |
|---|---|---|---|
| AB-021 C-301 | MH-2 to MH-3 8 in PVC | Permit east span: 244 ft Survey span: verify after alignment Total offset: pending | Open Confirm control fit and both coordinate components |
| AB-022 C-301 | MH-3 inlet survey point ID required | Permit invert: 2,223.33 ft Survey invert: enter verified shot Delta: survey − permit | Open Confirm datum, direction, and cited tolerance |
The blank cells are intentional. An independently checkable drawing does not fill evidence gaps with guesses. The 244-foot component is supported by tracked permit values; the survey span and compliance status remain open until aligned survey coordinates and a governing limit are confirmed.
How should the redline appear on the drawing?
The redline should place a numbered cloud at the affected feature and a compact note outside dense linework. A useful note reads: “AB-021: MH-2 to MH-3 plan position; permit east-coordinate span 244 ft; survey span pending verified alignment; see review log.” It says what is known without implying a failed tolerance.
Keep the plan and profile synchronized. If the plan view shows a shifted structure but the profile retains the permitted invert, flag both fields for review. Do not turn a measured difference into a design correction until the responsible professional has confirmed the match, datum, requirement, and disposition.
What can AsBuiltReview contribute to this example?
AsBuiltReview can prepare a first-pass comparison and produce review deliverables, while the reviewer remains responsible for the engineering judgment. The AsBuiltReview features page describes alignment, structure matching, horizontal offsets, elevation comparisons, pipe checks, spec citations, a redline PDF, a compliance report, an Excel review log, and a rough DXF.
The same page states the limits: DWG is not read directly, starter limits are placeholders, the rough DXF must be finished in CAD, and a licensed engineer confirms every finding. Those constraints define what the evidence supports. Source code can demonstrate the fictional fixture and calculation above; it cannot establish live runtime accuracy or professional approval.
What do reviewers ask about as-built drawing examples?
Reviewers usually ask what to preserve, how to label changes, and who can approve the result. Project requirements settle the final form.
What does a good as-built drawing example show?
A good as-built drawing example keeps the permitted value visible, adds the surveyed value, calculates the signed difference, identifies the source observation, and records the reviewer’s disposition.
Should an as-built drawing erase the permitted condition?
Keep enough of the permitted condition to make each change understandable. The governing contract and authority decide the required symbology and final presentation.
How should a manhole discrepancy be labeled?
Label the structure, sheet, measured field, permit value, surveyed value, units, signed difference, source point, and issue status. Add the governing requirement only after its citation is verified.
Can software approve an as-built drawing?
No. Software can prepare measurements and review files, but the responsible licensed professional must confirm the source data, matches, requirements, findings, and final drawing.