Construction As-Built Drawings: Build a Discrepancy Register

For a construction as-built drawing review, compare each surveyed asset with the permitted drawing, calculate the difference, and record the evidence and decision under one issue ID. A dependable register keeps a measured discrepancy separate from the later judgment about tolerance, acceptance, or correction.

Construction as-built drawing with a permitted manhole, surveyed observations, numbered redline, and discrepancy register row.
Illustration: one permit feature, its survey evidence, and a numbered drawing revision share the same register ID. This is a diagram, not a product screenshot.

What are construction as-built drawings used for?

Construction as-built drawings preserve the supported field condition at project completion and show how it differs from the construction set. For buried civil work, that can include structure position, rim and invert elevations, pipe size, material, slope, or a feature that was added or omitted.

The drawing is only one part of the record. Survey observations establish measured conditions; inspection notes, approved changes, and project requirements explain why a change occurred and how it should be treated. Keep those sources attached to the issue instead of compressing them into an unexplained red mark.

Caltrans’ Construction Manual procedure for as-built plans says field changes are transferred to the original CADD files and lists flow-line elevations and sewer locations among the information included on its final plans. It also sends the final drawings to the resident engineer for review and signature. Those are Caltrans requirements, not a universal discrepancy-register standard; the controlling contract, agency rules, and professional review still govern each project.

How do you review surveyed construction against permitted drawings?

Review surveyed construction against permitted drawings in five passes, with each pass adding evidence to the same issue row.

  1. Lock the sources. Record the permitted sheet and revision, survey file and date, units, horizontal coordinate system, and vertical datum. A comparison cannot be repeated if either source later changes silently.
  2. Confirm identity. Match the surveyed observation to the intended plan feature. Preserve the survey point ID and raw description even when a reviewer assigns a structure name. The guide to survey point IDs and structure names covers this crosswalk in detail.
  3. Compare one field at a time. Calculate horizontal position, rim, inlet invert, outlet invert, diameter, and material as separate checks. Use signed differences so the direction of an elevation change remains visible.
  4. Test the requirement. Cite the exact contract, specification, permit note, or approved change that controls the field. A measured difference alone does not establish noncompliance.
  5. Carry the disposition back. Use the issue ID on the drawing cloud, register row, reviewer note, and final response. Close the row only when the drawing and evidence agree.

If the installation is still exposed, the before-backfill field record helps capture measurements while they can still be checked directly.

What does an independently checkable construction example look like?

An independently checkable construction example names its source values, performs visible arithmetic, and states what the result cannot prove. The repository’s fictional permit fixture defines MH-2 as follows:

{ name: "MH-2", x: 5248, y: 5032, rim: 2238.9, invIn: 2228.4, invOut: 2228.3 },

The permit depth check is 2,238.90 ft − 2,228.40 ft = 10.50 ft from rim to inlet invert. That 10.50-foot result verifies the permitted values were transferred consistently into the review row; it is not a field depth, a tolerance, or proof of compliance.

A reviewer would next enter the matched surveyed rim and inlet invert, compute the surveyed depth, and subtract the 10.50-foot permit depth. If either survey observation lacks a verified point ID or datum, the row stays open. This restraint matters because source-code fixtures demonstrate repeatable arithmetic, not live import accuracy or conditions at a real construction site.

What should the discrepancy register contain?

The discrepancy register should contain enough context for another reviewer to reproduce the comparison without guessing which files, features, or requirements were used.

Copyable construction as-built discrepancy register
IssueFeature and sourcesMeasured comparisonRequirement and disposition
AB-031MH-2 inlet
Permit: C-301, Rev 2
Survey: [file / point ID]
Permit depth: 10.50 ft
Survey depth: [rim − inlet]
Delta: [survey − permit]
Requirement: [document / section]
Status: Open
Owner: [name]
[ID][asset / sheet / revision]
[survey file / observation]
[permit / survey / signed delta]
[units and datum]
[citation / status / decision]
[reviewer / date]

Copy the headings into a spreadsheet or issue system. Keep “measured comparison” and “disposition” in separate columns. That separation allows a reviewer to correct a cited requirement without overwriting the underlying survey calculation.

How should discrepancies appear on the construction drawing?

Discrepancies should appear as compact, numbered revisions that leave the original permitted condition legible. Use the revision symbols, issue references, and approval process required by the project at hand. Keep the issue ID and the earlier permitted value available so a reviewer can trace the change.

A practical note for the worked row would read: “AB-031: MH-2 inlet depth; permit 10.50 ft; survey comparison pending verified rim and inlet shots; see register.” It identifies the known value and the evidence gap without declaring a failure. Once the survey values and governing criterion are confirmed, revise the note and disposition together.

What can AsBuiltReview prepare for the reviewer?

AsBuiltReview can prepare a first-pass comparison, measured findings, and files for human review. The AsBuiltReview features page lists structure matching, horizontal offsets, elevation and pipe checks, spec citations, a redline PDF, a compliance report, an Excel review log, and a rough DXF.

The same product page sets important limits: DWG files are not read directly, starter limits are placeholders, the rough DXF needs finishing in CAD, and a licensed engineer confirms every finding. The feature set supports organizing the workflow described here. It does not support claims that the application certifies a drawing, resolves an ambiguous asset match, or replaces review of the governing documents.

What do teams ask about construction as-built drawings?

Teams usually ask which differences belong on the drawing, what the register should retain, and who makes the final decision.

What should construction as-built drawings show?

Construction as-built drawings should show supported changes from the permitted condition, retain enough original information to understand each change, and connect every revision to its source observation and disposition.

Should every survey difference become a redline?

No. First confirm the asset match, units, coordinate system, vertical datum, drawing revision, and survey quality. Record the measured difference before deciding whether the contract requires a drawing change.

What belongs in a construction discrepancy register?

Include an issue ID, sheet and feature, permit and survey sources, compared values, signed difference, governing reference, status, owner, and final disposition.

Can AsBuiltReview approve an as-built drawing?

No. AsBuiltReview prepares a first-pass comparison and review files. A licensed engineer confirms every finding, and the product does not stamp, certify, or approve work.