How to Review As-Built Drawings Against Permit Plans

As-built drawings record construction as it exists, including field changes from the permitted design. To review civil as-built drawings, align the survey with the permit plans, match each structure and pipe, calculate the differences, and place every supported discrepancy in a redline register. Leave uncertain matches open and have the responsible licensed professional confirm the findings.

Civil plan-sheet comparison showing a permitted manhole, its surveyed position, a redline offset, and a discrepancy register.
Illustration: the survey position is checked against the permitted manhole, then carried into a traceable discrepancy register.

What are as-built drawings?

As-built drawings are the project drawings revised to show actual construction rather than design intent alone. They should make field locations, elevations and approved changes understandable to someone who was not present during construction.

The Indian Health Service manual provides one bounded federal example. It requires record drawings, which it parenthetically calls as-built drawings, for IHS construction projects unless otherwise noted. That is an IHS requirement, not a universal definition or checklist. Your contract, utility standard and jurisdiction still control your project.

What should you check before comparing as-built drawings?

Before comparing as-built drawings, confirm that the permit set, survey and governing requirements belong to the same project and coordinate basis. A precise calculation against the wrong revision is still wrong. If two files name different datums, stop there and resolve the conflict.

  • Record the permit drawing revision and survey date.
  • Confirm units, horizontal coordinate system and vertical datum.
  • Identify the control points used to align the files.
  • Check structure names, pipe directions and survey descriptions before matching.
  • Load the project’s actual tolerance and citation for each check.

Keep imported observations intact while you prepare matches. The earlier guide to survey point IDs and structure names shows why one manhole may have separate rim and invert observations even though the plan label repeats.

How do you review as-built drawings against permit plans?

Review as-built drawings against permit plans in six passes, moving from file identity to documented disposition. This order keeps a bad alignment or weak match from turning into dozens of convincing but false discrepancies.

  1. Freeze the source set by noting each file name, revision, date and datum before measuring.
  2. Align on reliable control such as property corners or monuments. Inspect rotation, scale and residual error, and do not use a displaced structure to force the fit.
  3. Match each surveyed asset to the permit structure using names, descriptions, connected runs and geometry. Put unmatched items on their own list.
  4. Calculate horizontal offset, rim and invert deltas, pipe length, slope, cover and utility separation where the source data supports them.
  5. Compare each measured value with the cited project requirement. A number with no governing source is an observation, not a compliance decision.
  6. Close the paper trail with an issue ID, sheet location, measured values, rule citation, status and reviewer note.

A pass belongs in the review record too. It shows that the feature was checked, which source values were used and which requirement governed the result.

What does a worked manhole review look like?

A worked manhole review separates the measured elevation difference from the rule used to judge it. The repository’s demo fixture sets the permitted rim for MH-3 at 2,234.20 ft and its survey generator applies a -0.15 ft change. Adding those tracked inputs produces a generated survey rim of 2,234.05 ft.

Worked comparison of the permitted and surveyed MH-3 rim elevation
Review fieldValueHow it was obtainedWhat it means
Permit rim2,234.20 ftDemo permit fixtureDesign elevation
Fixture change-0.15 ftDemo survey generatorTracked fictional adjustment
Generated survey rim2,234.05 ft2,234.20 + (-0.15)Computed fixture value
Signed delta-0.15 ft2,234.05 - 2,234.20Generated survey is 0.15 ft low

The source-backed arithmetic is 2234.20 + (-0.15) = 2234.05 ft. Subtracting the permit rim from that generated value returns the fixture’s -0.15 ft change. That is a measured demo difference, not a compliance outcome: a reviewer still needs the project’s cited vertical tolerance before calling it a pass or failure.

This fixture supports only the fictional inputs, generated value and arithmetic shown here. It does not prove a live upload parsed correctly, a production result is accurate, a real structure moved or a jurisdiction would accept the drawing.

How should you document discrepancies on as-built drawings?

Document as-built drawing discrepancies with enough source detail for another reviewer to repeat the comparison. A red cloud without the permit value, surveyed value and governing rule leaves the next person measuring the same feature again.

Use these columns as a copyable discrepancy-register template:

Example discrepancy register row for the MH-3 rim review
Issue / sheetFeature and sourceMeasured comparisonRule, status and note
AB-014
C-301
MH-3 RIM
survey rim observation
Permit 2,234.20 ft
Survey 2,234.05 ft
Delta -0.15 ft
Project vertical tolerance: verify citation
Open
Confirm datum and governing limit

Keep the issue open until the datum, source observation and governing limit are confirmed. If the engineer accepts the condition, record who made the decision, the date and the reason. Do not erase the measured difference when the disposition changes.

Next step: prepare the resubmittal

AsBuiltReview compares supported permit and survey files, applies reviewer-selected project rules, and produces review outputs, while a licensed engineer confirms every finding. Prepare a resubmittal checklist from the open findings, or run a first-pass review.

What can AsBuiltReview check in an as-built drawing review?

AsBuiltReview can prepare a first-pass comparison of structures and pipes, then produce review files from the findings. The AsBuiltReview feature summary lists alignment, structure matching, horizontal offsets, rim and invert differences, pipe length and slope, minimum cover, spec citations, redline PDF, compliance report, Excel review log and a rough DXF.

The product’s limits belong beside its capabilities. DWG must be saved as DXF or exported as LandXML. Starter rule values require replacement and citations. The rough DXF needs completion in CAD, and a licensed engineer confirms every finding. Automation can shorten the measuring pass; it cannot decide that incomplete evidence is good enough.

What do reviewers ask about as-built drawings?

Reviewers ask about the contents, responsibility and naming of as-built drawing packages. The project contract and reviewing authority settle the final requirements.

What should be shown on civil as-built drawings?

Civil as-built drawings should show the installed locations, elevations, dimensions and material details required by the contract or reviewing authority. For utility work, that often includes structure locations, rim and invert elevations, pipe sizes, slopes, crossings and field changes.

Are as-built drawings the same as record drawings?

Do not assume the terms are interchangeable. This guide does not rely on a universal distinction; use the definitions and deliverables in the project contract and reviewing authority's requirements.

Who should review civil as-built drawings?

The responsible licensed professional should confirm the survey basis, matching, calculations, governing requirements and final disposition. Software can prepare a first pass, but it cannot approve, certify or stamp the work.

What if survey names do not match the permit plans?

Keep the source survey ID and raw description, propose a separate plan structure match, and record the evidence for that choice. Leave the match unresolved when the description, geometry and connected runs do not support one answer.