Building a resubmittal checklist from open comments
A resubmittal checklist turns open review issues into a project-controlled handoff that preserves the fields needed for follow-up and verification. It is a manual project document, not a sheet that AsBuiltReview sends to a contractor.
Start with the exported Review Log
The Review Log exports these columns: Issue, Status, Feature, Check, Found, Allowed, Spec, Document, Section, Citation text, Review status, and Reviewer note. Filter on Review status rather than Status: Status reports the generated check result, while Review status records the reviewer’s Open, Accepted, Resolved, or Waived disposition.
Finding ID, Contractor Response, Verified, owner, due date, and a cross-cycle identifier are not current Review Log column names. Add any of them to the separate checklist only when the project team needs them, and label them as project-controlled fields.
Choose the handoff fields
- Keep the exported Issue, Feature, Check, Found, Allowed, citation fields, Review status, and Reviewer note needed to understand each open item.
- Add a stable project-controlled ID when the item must be followed across review cycles.
- Add an owner and next action so responsibility is explicit. Add a due date only when the project’s process supplies one.
- Give the checklist to the appropriate project participant through the team’s normal submittal process. AsBuiltReview does not send it.
- Record verification evidence after a reviewer examines the next submittal; do not treat a response or revised label as proof by itself.
Copyable fictional example
| Project ID | Issue | Feature / check | Found / allowed | Project citation | Review status / note | Owner / next action | Contractor response | Verification evidence |
|---|---|---|---|---|---|---|---|---|
| [project carry-forward ID] | [app issue #] | [asset] / [check] | [measured value] / [required value] | [project citation] | Open / [reviewer note] | [owner] / [next action] | [project team entry] | [evidence reviewed and result] |
This placeholder preserves the measured value, required value, and governing project citation without inventing a standard, tolerance, RFI, contractor response, or corrected result.
For items that span review cycles, label unresolved findings for the next submittal. When the source files and project rules are ready, run the first-pass review.